Cost of poor quality % practice

Work out what share of a project’s spending went on fixing failures: internal failure cost (before handover) plus external failure cost (after handover), divided by the actual project cost to date, × 100. Your answer marks itself as you type: a tick when it is right, a cross when it needs another look. Stuck? Open the working.

Example 1
0 of 1 correct

Type the cost of poor quality as a percentage to 2 decimals (for example X or X.00). The box turns green when it is correct.

Your answer is correct