Contingency coverage ratio practice
Work out whether the contingency left can cover the expected cost of the risks still open: the original contingency minus what has been spent, divided by the total risk exposure of the open risks. Your answer marks itself as you type: a tick when it is right, a cross when it needs another look. Stuck? Open the working.
This translation is a draft. Spot a translation mistake? Tell us
Type the contingency coverage ratio to 2 decimals (for example X or X.00). The box turns green when it is correct.
Your answer is correct
Well done. Try another example to make sure it sticks, or see how Praxis Practice™ can take you further.